Railway Statistics

Subway Infrastructure

  • Since the launch of Seoul Subway Line 1 between Seoul Station - Chungryangli Station on August 15, 1974, the government has invested KRW  26.9984 trillion in subway network construction as of April, 2008 and 16 subway lines stretching 504.1km in total are now in operation in Seoul, Busan, Daegu, Incheon, Gwangju and Daejon. In terms of regional breakdown, Seoul has 8 subway lines running 286.9km, Busan 3 lines of 96.0km, Daegu 2 lines stretching 57.3km, Incheon 1 line of 22.9km. Gwangju 1 line of 20.5km and Daejon 1 line running 20.5km.
  • As of April, 2008, there are 480 subway stops nationwide, including 265 in Seoul, 94 in Busan, 56 in Daegu, 23 in Incheon, 20 in Gwangju and 22 in Daejon. Total number of rolling stock adds up to 5,041 units, 3,505 in Seoul, 776 in Busan, 384 in Daegu, 200 in Incheon, 92 in Gwangju, 84 in Daejon which add up to 650 trainsets.
  • Metropolitan subways carry 7,461,000 persons per day in total as of the end of '07, which break down into 6,213,000 in Seoul, 651,000 in Busan, 294,000 in Daegu, 201,000 in Incheon, 38,000 in Gwangju and 64,000 in Daejon. As of ’07, in annual terms, passenger carrying records are 2,723 million persons in total, 2,268 million in Seoul, 238 million in Busan, 107 million in Daegu, 73 million in Incheon, 14 million in Gwangju and 23 million in Daejon.

Operating Status by Metropolitan Subway Line (As of April, 20, 2008)

※ In : ea.

Operating Status by Metropolitan Subway Line (As of April, 20, 2008)
Classification Total Seoul Total Seoul Metro
Line 1 Line 2 Line 3 Line 4
Section 16 lines 8 lines Seoul St.~Chungryangli Seongsu~Seongsu Jichuk~Suseo Danggogae~Namtaeryung
Distance (km) 504.1 286.9 7.8 60.2 35.2 31.7
Stops (ea.) 480 265 10 50 31 26
Trip time (min.) - - 16 87 62 53
Trains (ea.) 5,041 3,505 160 834 480 470
Trainsets 650 (4-10) 399 (4-10) 16 (10) 88 (4-10) 48 (10) 47 (10)
Headway (min.) Normal - - 4.0 6.0 6.5 5.5
R/H - - 3.0 2.5 3.0 2.5
Scheduled speed(km/h) - - 29.3 33.7 34.1 35.9
Carrying capacity (1k persons/day) 7,461 6,213 465 1,938 702 818
’07 carrying record (1m persons) Carrying 2,723 2,268 170 707 256 299
Boarding 2,090 1,654 112 536 190 224
Inflow 633 614 58 171 67 74
Const. cost (KRW 100m) 268,874 122,720 330 10,712 10,304 8,315
Const. period - - 1971~1974 1978~1996 1980~1993 1980~1994
Ground-breaking - - ’71. 4.12 ’78. 3. 9 ’80. 2.29 ’80. 2.29
Commissioning (service launch) - - ’74. 8.15 ’80.10.31 ’85. 7.12 ’85. 4.20
Operating Status by Metropolitan Subway Line (As of April, 20, 2008)
Classification Total Seoul Total Seoul Metro
Line 5 Line 6 Line 7 Line 8
Section 16 lines 8 lines Banghwa~Sangildong/Macheon Eungam~Bonghwasan Jangam~Onsu Moran~Jamsil
Distance (km) 504.1 286.9 52.3 35.1 46.9 17.7
Stops (ea.) 480 265 51 38 42 17
Trip time (min.) - - 83~87 70 87 31
Trains (ea.) 5,041 3,505 608 328 499 126
Trainsets 650 (4-10) 399 (4-10) 76 (8) 41 (8) 62 (8) 21 (6)
Headway (min.) Normal - - 5.0 6.0 5.0 6.0
R/H - - 2.5~3.0 4.0~5.0 2.5~4.0 4.5~6.0
Scheduled speed(km/h) - - 32.7 30.1 32.3 34.2
Carrying capacity (1k persons/day) 7,461 6,213 815 434 817 224
’07 carrying record (1m persons) Carrying 2,723 2,268 298 158 298 82
Boarding 2,090 1,654 214 108 214 56
Inflow 633 614 84 50 84 26
Const. cost (KRW 100m) 268,874 122,720 31,210 25,496 27,851 8,502
Const. period - - 1990~1996 1994~2001 1990~2000 1990~1999
Ground-breaking - - ’90. 6.27 ’94. 1. 8 ’90.12.28 ’90.12. 2
Commissioning (service launch) - - ’95.11.15 ’00. 8. 7 ’96.10.11/td> ’96.11.23

※ Inflow : passengers getting on in sections of other lines→getting off in sections of a certain line, Outflow : passengers getting on in sections of a certain line→getting off in sections of other lines

※ Carrying = boarding + inflow

※ As of April, 20, 2008

Operating Status by Metropolitan Subway Line (As of April, 20, 2008)
Classification Busan TC
Total Line 1 Line 2 Line 3
Section 3 lines Sinpyeong~Nopo Jangsan~Yangsan Suyoung~Daejeo
Distance (km) 96.0 32.5 45.2 18.3
Stops (ea.) 94 34 43 17
Trip time (min.) - 62 84 34
Trains (ea.) 776 360 336 80
Trainsets 121 (4-8) 45 (8) 56 (6) 20 (4)
Headway (min.) Normal - 6.0 6.5 7.0
R/H - 4.0 4.5 5.0
Scheduled speed(km/h) - 31.5 32.3 31.9
Carrying capacity (1k persons/day) 651 375 215 61
’07 carrying record (1m persons) Carrying 238 137 79 22
Boarding 238 137 79 22
Inflow - - - -
Const. cost (KRW 100m) 55,699 9,751 28,553 17,395
Const. period - 1981~1994 1991~2007 1996~2005
Ground-breaking - ’81. 6.23 ’91.11.28 ’97.11.25
Commissioning (service launch) - ’85. 7.19 ’99. 6.30 ’05.11.28
Operating Status by Metropolitan Subway Line (As of April, 20, 2008)
Classification Daegu MSC Incheon RTC Gwangju MRTC Daejon
Total Line 1 Line 2
Section 2 lines Daegok~Ansim Moonyang~Sawol Gyeyang~Dongmak Nokdong~Pyungdong Panam~Banseok
Distance (km) 57.3 28.3 29.0 22.9 20.5 20.5
Stops (ea.) 56 30 26 23 20 22
Trip time (min.) - 50.5 49 43 38 40
Trains (ea.) 384 204 180 200 92 84
Trainsets 64 (6) 34 (6) 30 (6) 25 (8) 23 (4) 21 (4)
Headway (min.) Normal - 7.0 7.0 8.5~10.0 8.0~10.0 10.0
R/H - 5.0 5.0 4.5~6.0 5.0~7.0 5.0~6.0
Scheduled speed(km/h) - 30.8 34.3 31.9 34 31.6
Carrying capacity (1k persons/day) 294 166 128 201 38 64
’07 carrying record (1m persons) Carrying 107 60 47 73 14 23
Boarding 107 60 47 73 14 23
Inflow - - - 19 - -
Const. cost (KRW 100m) 38,517 15,187 23,330 16,349 16,658 18,931
Const. period - 1991~2002 1996~2005 1993~1999 1996~2007 1996~2007
Ground-breaking - ’91.12. 7 ’96.12.19 ’93. 7. 5 ’96. 8.28 ’96.10.30
Commissioning (service launch) - ’97.11.26 ’05.10.18 ’99.10. 6 ’04. 4.28 ’06. 3.16

Source : Regional Metropolitan Subway Dept., Ministry of Land, Transport & Maritime Affairs